Timeline
Edmond Place completions date: November 2010
- January 2007 PARC submits a response to a city-wide RFP
- April 2007 PARC is awarded the development of the now city-owned property
- June 2007 the property is identified as a potential heritage designation
- December 2007 property is designated a heritage site
- August 13th 2008 Committee of Adjustment (completed successfully)
- November 2008 – February 2009 - remediation & consolidation
- September – February 2009–detailed architectural drawings are prepared
- February - March 2009 – prepare tender documents
- March 2009 – PARC equity portion due
- April 2009 – go to tender
- May 2009 – select contractor
- June/July 2009 – begin construction
- June 2009 – October 2010 – construction period
- November-December 2010 – commissioning and occupancy approval period
- January 2011 – tenants move-in